Home

Progress

December 2023

Completed the installation of facilities in the Physical and Chemical Laboratory

Completed the installation of facilities in LC Laboratory

November 2023

Completed the installation of facilities in the Precision Balance Room

Completed the Reference Standard Room

October 2023

Completed the installation of facilities in the Preparation Room

Completed the Sample Preparation Room

September 2023

Completed the installation of facilities in the Preparation Room

Completed the lobby construction

Completed the installation of facilities in LC Laboratory

Completed the installation of facilities in Physical and Chemical Laboratory

August 2023

*Installation of lab benches and cupboards in the Preparation Room

*Installation of lighting in the Lobby

July 2023

*Installation of gas cylinder cabinets

*Installation of lab benches and fume hoods in the Physical and Chemical Laboratory

June 2023

*Installation of concrete floor and windows in the GC and GC-MS Laboratory

*Installation of concrete floor in the Spectroscopy Laboratory

May 2023

*Completed the construction of the interior walls

*Installation of weak current system

April 2023

*Disscussion of construction plan with the contractor

*Preparation of socket wiring

March 2023 

*Preparation of fire hose materials

*Construction of the exterior walls

February 2023 

*Construction of partition walls

*Creation of door opening

January 2023 

*Design of MCTCM building

*Day 1 of the construction